Dedicated to Building Your Vision  

Click here to edit subtitle

Services

Gypsum Board Assemblies

  • Metal Framing & Suspension Systems
  • Cold-Formed Metal Framing
  • Curtain Wall Framing
  • Hanging Gypsum Wall Board
  • Taping Gypsum Wall Board (All Levels)
  • Skim Coating
  • Aluminum Trims & Reveals
  • GFRG Columns, Shapes & Other Specialty Products
 

Acoustical Treatments 

  • Suspended Ceiling Systems
  • Acoustical Wall & Ceiling Panels
  • Compsso/Axiom "Island" Trims
  • Metal & Wood Ceilings
 

Carpentry

  • Frames 
  • Doors 
  • Hardware (Both Metal & Wood)
  • Rough Carpentry

Other services
  • Comercial Grade Millwork 
  • Interior Demolition 
 

Completed Fast Track Projects 

Project Name: UNO Highschool

Project Owner: UNO Charter Schools

Brief Project Description: Drywall & Taping services

Project Size: 3 stories – about 7,000 sheets of drywall

Date of Project Commencement: April 2013

Percent of Work Completed: 100%


Project Name: UNO Rogers Park School 

Project Owner: UNO Charter Schools

Brief Project Description: Drywall assemblies, demolition, & T&M Finish carpentry.

Project Size: 10,000 Sq ft

Date of Project Commencement: 08.07.12

Date of Actual Completion: 09.08.12

Percent of Work Completed: 100%


Project Name: British School of Chicago Chicago, IL

Project Owner: British School of Chicago

Brief Project Description: Provide and install lay-out, framing, drywall, insulation and finish tape level 4 (Renovation/Expansion)

Project Size: 5,000 Sq ft

Date of Project Commencement: 07.09.13

Date of Actual Completion: 07.31.13

Percent of Work Completed: 100%


Project Name: 35 E. Wacker 13th Floor

Project Owner: DUS Management Inc.

Contact #: Jim Swicionis 708.404.2793

Brief Project Description: Provide and install lay-out, framing, drywall, insulation and finish tape level 4.

Project Size: 18, 000. Sq ft

Date of Project Commencement: 12.16.12

Date of Actual Completion: 01.06.12

Percent of Work Completed: 100%


Project Name: 35 E. Wacker 10th Floor

Project Owner: DUS Management Inc.

Brief Project Description: Demolition

Project Size: 19,000 Sq. Ft.

Date of Project Commencement: 12.02.11

Date of Contracted Completion: 12.19.11

Date of Actual Completion: 12.17.11

Percent of Work Completed: 100%here to edit text


Project Name: Chase Bank – Scattered Sites 20 total

Project Owner: Bovis Lend Lease

Brief Project Description: Full carpentry services 

Project Size: 1, 800. Sq ft

Date of Project Commencement: 08.06.12

Percent of Work Completed: 20 banks completed


Project Name: McDonald’s  Scattered Sites, IL

Project Owner: Bovis Lend Lease

Brief Project Description: Full carpentry services including roof/parapet work & ACT (Brand improvement renovation)

Project Size: 4, 500. Sq ft

Date of Project Commencement: 9.24.12 

Estimated Date of completion: 11.24.12

Percent of Work Completed: 100%


Project Name: Charter One Bank- Chicago, IL

Project Owner: Charter One/Citizens Bank

Brief Project Description: Demolition, Carpentry, Drywall and ACT.

Project Size: 9,500 Sq Ft.

Date of Project Commencement: 09.02.11

Date of Contracted Completion: 11.22.11

Date of Actual Completion: 11.17.11

Percent of Work Completed: 100%


Project Name: Ulta Beauty – Dekalb, IL

Brief Project Description: Provide and install lay-out, framing, drywall, insulation and finish tape level 4 (Build out of new space)

Project Size: 11, 000. Sq ft

Date of Project Commencement: 07.30.12

Date of Actual Completion: 08.16.12

Percent of Work Completed: 100%


Project Name: National Able Network- Chicago IL

Project Owner: Chicago Transit Authority

Brief Project Description: Furnish labor, material and equipment to complete the drywall assemblies, act ceiling assemblies and demolition.

Project Size: 7,600 Sq Ft.

Date of Project Commencement: 03. 04.11

Date of Contracted Completion: 05. 06. 11

Date of Actual Completion: 05.06.11

Percent of Work Completed: 100%